DEVELOPMENT – FURNACE SIDINGS-FOOTBRIDGE (STEP 1.3.2)
The ‘Hinckley’ footbridge (uploaded 24 October 2008)
There seems to
be poplar misconception amongst visitors that all preserved railways in Wales and the
West must be Great Western. In the case
of the PBR, this is certainly not true. Our
history section will show that the part of the line between the Whistle Inn,
through Furnace Sidings down to Blaenavon (High Level) was built by the
Brynmawr and Blaenavon Railway in 1866.
In reality the B&BRly was really the all-powerful London & North
Western Railway (LNWR) in sheep’s clothing.
In 1923, at the grouping imposed by the government of the day, the LNWR
became a constituent of the mighty London Midland and Scottish Railway (LMS), and so it remained until
nationalisation produced British Railways in 1948. It is true that the line was worked by GWR
engines in later days, but retained LNWR and LMS signals to the end. However, the inescapable fact was that it’s
infrastructure, such of it that remained until later days was pure LNWR. Now although Furnace Sidings never even
existed as a station prior to preservation, we felt honour bound to at least
make it suggestive of an LNWR backwater.
When the notion
of a second platform and a linking footbridge was being considered, it was with
LNWR ‘furniture’ in mind. It was a pure
stroke of good fortune that round about this time we became aware of a genuine
LNWR footbridge in store at the Rushden Historical Transport Society in Northampton, and that they
wanted to dispose of it. A visit to Northampton on a sunny day
in October 2006 revealed a beautiful station building, both inside and out, and
an impressive LMS signal box, but the footbridge had caused them problems. It was poor when they acquired it fifteen
years previously, and after all that time in outside storage, it had suffered
grievously.

The main deck is on the left, and the two towers,
one threaded in the other lie on their sides on the right. On the main deck the bottom angle had
rotted beyond redemption, and the side plates were holed in a number of
places. Behind can be seen the typical
LMS signal cabin
|

Member Alastair Warrington stands close to the top
of one of the towers. The cast trusses
were in good condition, and retained a certain ‘heavyweight’ LNWR charm. The legs had not only been burnt off, close
to their bases, but had suffered very severe corrosion
|

There were some interesting details, as the cast supports
for the handrail on the stair portion of the main deck illustrate
|

Some of the side walls would need complete
reconstruction. The presence of soil
and weeds within the structure served only to accelerate corrosion
|

The stair flight side walls were in generally very
poor condition, and this photo shows the bottom of the heavy cast newel
post. The base of this post is in good
condition, but several had pieces cracked or missing at the base
|

Oh, for a station waiting room like this one. Now used as a member’s bar in the main
building.
|

By the time we got the main deck to Furnace
Sidings on a rotten wet day in early November, our enthusiasm for this bridge
had been tempered by thoughts of ‘What on earth have we let ourselves in
for?’, and our confidence started to wane.
|

The delicate job of offloading the main deck off
the lorry onto terra firma was undertaken by a second lorry fitted with a
hi-ab unit.
|

Volunteer
and ace welder Derek considers how he is going to put the rest of tower 1
together
|

-and
here is the completed tower. Getting
it upright safely proved to be a difficult job
|

A
detail showing the stair flight bracket and the heavy cast spandrel that
supports the main deck
|

On 27 August 2008 was a day of typical low cloud, as the local transport firm was called
in once again to move the tower onto the platform.
|

It was a tricky job with the lorry reversing up
the grade, and often slipping – and it’s always worse when someone’s
watching.
|

Finally, with the hi-ab at absolutely full
stretch, the tower was dropped to within an inch of its final position.
|

Looking strangely isolated we see the tower on the
rather barren platform 1 in this view looking north east
|

Viewed straight on, the tower appears to lean,
with the platform straight. In fact it
is the platform that is not level- the tower is dead plumb
|

A week later on 7 September, it’s Derek once again
who grouts the tower into its concrete base with resin anchor bolts to make
sure it stays put!
|
News on the ‘Hinckley’
footbridge (uploaded 15 April 2009)
The winter has seen a lull in the proceedings since
Derek was involved fixing the loco shed roof which had blown off during the
winter gales, and it was far too cold and damp to attempt to paint the
footbridge, but eventually Spring 2009 arrived and work resumed.

In mid-February the repaired stair flight walls
arrive on Platform 1. The flower bed
under the posts of the running-in board posts would be an early casualty
img_2022rr
|

The first flight wall went in without too much of
a fight, a few days later - but it was
the Manitou’s jumbo tyres which laid waste to the flower bed.
img_2028rr
|

Both flight walls are on but there is a definite
twist on the left hand wall, we suspect due to poor storage conditions at
Rushden
img_2037rr
|

With the weather a little warmer and days slightly
longer, the laborious business of chipping away old paint gets underway, as
volunteer Bev W attacks the tower with a variety of dangerous looking
implements
Img_2038rr
|

Not
really related to the footbridge, but we knew that we were going to have to
move the old ‘station building’ (an old banana van) before construction of
its replacement could begin. We
planned to do this late in 2009. The
chance arrival of a crane on site doing something quite different decided a
rapid re-deployment on Platform 1 as the van was moved south of the bridge,
where it teeters on the south end of the platform.
img_2090rr
|

Not all our plans are trouble free in the
execution. In this case the van was
lifted – and left its floor behind. A
pity this, as we now have even more work if we are to restore the van. It’s worth doing, as there are only one or
two in preservation, and the sight of one, with its characteristic yellow
spot would make a colourful addition to our demonstration freight train
Img_2088.
|

In early April, the newel posts were fixed to the
bottom ends of the flight walls and concreted into position. Straining bars
had to be employed to force the twisted flight wall back into shape, whilst the
concrete set. A few days later the
bars were removed and, thank goodness, the flight walls remained perfectly
aligned. Here volunteer Eric (he of
Eric’s Emporium’) examines the work, whilst Derek looks on, having just
welded the ‘Furnace Sidings’ sign permanently into position.
img_2187rr
|

Its Easter Sunday and a fine Spring morning sees
platform 1 well patronised as passengers wait for the first train. In the background, the tower, topped by ‘Y
Ddraig Goch’ has been fully primed, including the newel posts. A new coat of undercoat/topcoat is being
applied now, which will bring the bridge a shade darker.
img_2280rr
|
More news on the ‘Hinckley’
footbridge (uploaded 12 June 2010)
It seems rather odd, but for some reason, updates
regarding progress on the Hinckley footbridge have been noticeable by their
absence. That is not, by any means, to
say that there has been no progress, far from it, though much of it has been
progressive in nature and with no obviously photogenic consequences that would
justify many images on this page. It has
been fifteen months since our last report, and the work has in fact been quite
dramatic. In a nutshell:
(a) The second tower has been
assembled and has been erected on site, though cannot yet be bolted down till the
main deck is installed. The tower
remains to be painted.
(b) The second tower flight walls
were sent to Barry Docks for welding and reconstruction. They have since been returned to Blaenavon
and are now in position ready to be bolted to No.2 tower. They still remain to
be painted.
(c) the newel posts for No.2
flight have been painted and remain in the yard.
(d) the big news is that the
extensive, and seemingly endless, welding work on the main deck is essentially
complete, and painting is well under way.
Wooden planking for the main deck and its related ascents (and for the
two flights) is to be ordered shortly. A
very few detailed welding jobs remain.
Now that it is becoming obvious that what started in
October 2006 as an ugly collection of rusting parts is about to emerge as a
swan (insoar as anything of LNWR design could ever be so described), less than
four years later, the political spotlight is undoubtedly turning to the
footbridge and there seems to be a gathering collective political will to get
the bridge erected during the summer. It
could be that the next update will the last on the footbridge and will record
its final lifting into place – and some images from a new viewpoint! Anyway, here are 22 images telling the story
to date.

Carrying tower No.1 complete from assembly on site
up to the platform was a difficult job, and it was decided to assemble tower
No.2 on the essentially unused platform 2.
Here the first of the legs makes the journey from the site yard
2351 – 26 Apr 09
|

The components start to arrive on platform 2. One of the newly primed legs in seen in the
foreground.
2398 – 3 May 09
|

Assembly begins – two legs are joined by three
heavy but attractive cast trusses. We has
always been worried that we might break one of the castings, which would as
likely as not would have rendered the whole bridge scrap, but, to date, there
have been no accidents
2415 – 3 May 09
|

With just one truss to go the assembly approaches
completion
2822 – 15 June 09
|

The other half of the fabrication team, George P,
keeps an eye on the proceedings as the last of the trusses is lowered into
position. As a note of explanation the
tower marked NW is in the south west, and vice versa. The markings relate to the positions at Hinckley, which have been-
re-orientated so that the stair flight points the opposite way.
2837 – 21 June 09
|

The same scene from a differing viewpoint. Derek steadies the frame and slackens some
bolts as Wayne E on the Manitou adjusts the final truss into place
2838 -21 June 09
|

The lift begins!
Platform 2 is tested well beyond its design limit as a lorry load of concrete
blocks, which happened to be passing, is commandeered into lifting tower No.2
with its hi-ab.
3055 – 22July 09
|

The tower teeters on its balance point. Note that the attitude of the tower is
incorrect, as, once swinging, it has to be turned through ninety degrees so
that the open side fitted with spandrels points across the rails to support
the main deck and the triangular gussets point southwards to support the
stair flights
3056 – 21 June 09
|

All that worry about getting the tower into
position and the whole job only took five minutes. Men from the local haulage firm remove the
lifting tackle from the bridge
3059 - 21July 09
|

Looking
the other way a few days later we see tower No.2 in repose. It is very close to its final position, but
needs to come in by 30mm after the main deck is slotted in.
3113
– 25 July 09
|
With tower No.2 in position it was now time to
concentrate on the main deck. There had already been some progress but now all
bridge effort could be directed to the main deck. Unfortunately there were many interruptions,
distractions, and diversions, but despite these the fabrication team always
managed to gravitate back to the bridge, so that although progress was slow, it
continued to move inexorably forward.

Due to the proximity of damp timber to the bottom
flange of the bridge (which would have supported the timber planking)the
flange had almost completed rotted away.
This is the ‘Achilles heel’ of this type of foorbridge. This corrosion demanded the complete
replacement of the bottom flange and of the first six inches or so of the
side panel. Here the new parts have
been bolted, but not yet welded into place
0092 – 16 Aug 09
|

Here’s a technical close-up of work in
progress. Nothing has been welded yet,
and the rivets have been replaced by high tensile friction bolts – not pretty
but effective. The corrosion on the
ascent is also severe but the bottom flange will live to fight another day,
though some further localised work in this area will be necessary.
0099 – 23 Aug 09
|

As can be seen in preceding images, corrosion of
the ‘ascent’ panels in severe, but here but the bottom flange is
acceptable. The technique used here is
to sandwich the defective plate between a new inner and outer plate. Here two plates can be seen tack welded
into place.
0649 – 8 Dec
2009
|

From further back it will be appreciated that the
sandwich technique employs no less than sixteen plates. The complex profile was obtained by means
of tracing through a roll of the webmaster’s wallpaper!
0658 – 14 Dec 09
|

Snow! With
only a sputtering arc to keep him warm, Derek B completes yet another two of
the sixteen panels.
0694 – 22 Dec
2009
|

The work continues by making a waterproof weld
along the top to keep the rain out. The bottom weld is intermittent in order
to allow any condensation to drain away
0807 – 17 Jan
2010
|

Along the ‘six-inch’ line a very deep penetrating weld
is required. The strengthening pillars
need particularly careful treatment when they are welded.
0990 - 7 Mar
2010
|

Derek B surveys the advancing weld. The nearest pillar has been ground to
confirm the quality of the weld
1017 – 14 Mar
2010
|

The plate
work is just about complete, but two stretcher bars under the main deck need
cutting off and replacing.
1103.-.4 Apr 2010
|

Here, in its full glory, the main deck. The repairs have left scars but this is not
expected to seriously detract from the overall appearance once the bridge is
painted.
1132 – 10 Apr
2010
|

Now it really does look as if completion is very
close. Derek B again, grit blasting
off any remaining paint, and surface rust, in readiness for the first primer
paint layer.
1294 – 30 May
2010
|

A high phosphate primer now stretches down the
length of the outside face, and, out
of sight, three quarters of the way down the inside. This is the face that will shortly face the
Whistle Inn.
1302 - 6 June
2010
|
So that is the current situation. We still have to install the cleats, which
support the footsteps, and we are having new brackets cast which will support
new handrails. It is expected that the
timber for the footsteps and decking will be ordered very shortly and these
must be installed. Since many of the
timbers will have profiled ends in order to provide clearance for bolt heads
and other bits and pieces this could prove to be quite time-consuming, and has
been recommended that this work is completed before the main deck is finally
lifted into position, in order to provide dimensional stability.
Click HERE to
return to Main Development page
